Supremes Settle Their Breach of Contract Action

Oblique_facade_3,_US_Supreme_CourtIt is not often that the Supreme Court of the United States entertains a contract issue (which is, coincidentally, one of the main reasons it is such a delight to teach contract law).  The Supreme Court did, however, recently settle a contract dispute of its own.

According to reporting by Tony Mauro at the National Law Journal:

The curious case of the trapezoidal windows at the U.S. Supreme Court is closed.

Documents filed recently in lower courts indicate that a contentious seven-year dispute over mistakes and delays in the renovation project at the high court has been settled.

“Everybody was worn out by the litigation,” Herman Braude of the Braude Law Group said this week. Braude represented Grunley Construction Company, the main contractor for the modernization project on the nearly 80-year-old building. “All good things have to come to an end,” he said.

The most contested feature of the litigation was the belated discovery by contractors that more than 150 large windows, many of which look out from justices’ chambers, were trapezoidal—not strictly rectangular. The building's persnickety architect, Cass Gilbert, designed them that way so they would appear rectangular from below, both inside and outside the building.

But Grunley and its window subcontractor failed to measure all four sides of the windows before starting to manufacture blast-proof replacements, so some of them had to be scrapped.

Grunley claimed it was not obliged to make the measurements, asserting that the government had “superior knowledge” of the odd shape of the windows that it should have shared with contractors. The company asked for an extra $757,657 to compensate for the extra costs of fabricating the unconventional windows.

But the federal Contract Appeals Board in 2012 rejected Grunley’s claim, stating: “We find inexcusable the firms’ failure to measure a necessary component of the windows prior to installation.”

Grunley appealed to the U.S. Court of Appeals for the Federal Circuit and placed other contract disputes before that court and the U.S. Court of Federal Claims. Both sides eventually agreed to settlement negotiations.

In February, both parties reported to the federal circuit that “the parties are now in the final process of closing out the underlying construction contract and settling various requests for equitable adjustment.” They also told the federal circuit that “the settlement discussion are at a very high level between the parties … and are being primarily led by the principals of each party, not the litigation counsel.”

Subsequent orders by both courts have dismissed the litigation, but no details of the settlement are available on the docket of either court.

Attempts to obtain details of the settlement have been unsuccessful so far. The Architect of the Capitol—the congressional agency that has jurisdiction over the Supreme Court building and was the defendant in the litigation—did not respond to a request for comment. The U.S. Department of Justice’s civil division, which handled the litigation for the architect's office, did not respond as of press time, and neither did anyone from the Supreme Court.

Braude, Grunley's attorney, was reluctant to give details. “The dollar figure doesn’t matter,” he said. But when pressed, Braude said his client “got some” of the $15 million in extra compensation it was seeking from the government, beyond its original $75 million contract for the work.

“Everybody agreed to an adjusted contract price that recognizes the budget limitations of the government,” Braude said, adding that the settlement was “satisfactory to all parties. Nobody was jumping for joy, but everybody was a little happy.” Braude also said the Supreme Court signed off on the settlement.

John Horan of McKenna Long & Aldridge, an expert on government contract disputes, said there is no general rule about the confidentiality of settlements, and sometimes “the government doesn’t go out of its way to make settlements public.” But a document spelling out terms of the agreement is sometimes made part of the public record or can be obtained through the Freedom of Information Act, he said. The Supreme Court and the Architect of the Capitol, an arm of Congress, are exempt from the FOIA.

The modernization project at the Supreme Court broke ground in 2003 and the target completion date was 2008, though some follow-up work is still underway. The court's aging infrastructure—including one of the oldest Carrier air-conditioners in existence—was the trigger for the project, which has cost an estimated $122 million overall.

More here.  Great basis for an exam hypo.  And, wow! -- to be the attorney that sues the Supreme Court!

http://lawprofessors.typepad.com/contractsprof_blog/2014/08/supremes-settle-their-breach-of-contract-action.html

Government Contracting, In the News, Labor Contracts | Permalink

TrackBack URL for this entry:

http://www.typepad.com/services/trackback/6a00d8341bfae553ef01a3fd4235bd970b

Listed below are links to weblogs that reference Supremes Settle Their Breach of Contract Action:

Comments

Post a comment