Saturday, June 24, 2017

Pipeline Company Lacks Standing to Challenge State Foot-Dragging for Construction Approval

The D.C. Circuit ruled yesterday that Millennium Pipeline Company lacked standing to sue the New York State Department of Environmental Conservation for its foot-dragging on Millennium's application for a water-quality certificate--a prerequisite for building a pipeline under the Clean Water Act.

The ruling means that Millennium's case against the state agency is dismissed. But it also means that Millennium can proceed directly to the Federal Energy Regulatory Commission to get direct approval for the pipeline, considering the state agency's consideration waived.

The case arose when Millennium petitioned the state agency for a water-quality certificate, required under the Clean Water Act as a first step in gaining FERC approval for the pipeline. The state agency sat on the petition for over a year, however, arguing that it was incomplete. Millennium then sued the state agency, asking for a court order to require the agency to act so that it could take its application on to FERC.

But the D.C. Circuit ruled that Millennium lacked standing. That's because under the Clean Water Act when a state agency delays a decision for a year, the agency is deemed to have waived its consideration, and the applicant can take the application directly to FERC. As a result, the court said that Millennium hadn't suffered any harm from the state agency; after all, the agency's inaction only meant that Millennium could go right to FERC. The court went on to say that Millennium could sue FERC if it rejects the application, but that's down the road.

None of this breaks new law--and Millennium surely would have known this--so why'd Millennium sue? Probably because it anticipated opposition from the state agency down the road, and it wanted to get state-agency approval on the record now in order to preempt later opposition. The court had an answer for that, too: FERC, not the state agency, has final say, and Millennium can later sue FERC for any disapproval or delay.

http://lawprofessors.typepad.com/conlaw/2017/06/pipeline-company-lacks-standing-to-challenge-state-foot-dragging-for-construction-approval.html

Cases and Case Materials, Jurisdiction of Federal Courts, News, Opinion Analysis, Standing | Permalink